Parking striping in Józsefváros

The renewal of parking regulations and road markings in Józsefváros is entering its next phase. The works are being implemented based on the decision of the local community, as one of the winning ideas of the 2025 Participatory Budget. As a result, it will make district parking more organized and safer, keeping the real needs of the residents in mind.

The implementation will take place in phases from mid-July, affecting Luther utca as well as several different parking lanes in Szigony utca.

The painting works will be carried out in stages by the staff of the Józsefvárosi Gazdálkodási Központ according to the following schedule:

DateLocationExact Description of the Affected Area
July 13, 2026Luther utca main parking lotSzeles Erika tér
July 14, 2026Szigony utca main parking lotOdd-numbered side, parallel and perpendicular parking lanes under the building
July 15, 2026Szigony utca main parking lotOdd-numbered side, the first inner perpendicular parking lane
July 16, 2026Szigony utca main parking lotOdd-numbered side, the second inner perpendicular parking lane
July 20, 2026Szigony utca main parking lotEven-numbered side, the second inner perpendicular parking lane
July 21, 2026Szigony utca main parking lotEven-numbered side, the first inner perpendicular parking lane
July 22, 2026Szigony utca main parking lotEven-numbered side, parallel and perpendicular parking lanes under the building

Please note: Do not park out of habit. Please pay attention to the posted signs and move your vehicle away from the parking spaces closed for the duration of the painting. Thank you for your patience and understanding!

You can find information about previous parking space painting works at the following link: Parking Lot Striping is Scheduled to begin in Józsefváros – JGK

Józsefvárosi Gazdálkodási Központ
Városüzemeltetési Igazgatóság

📍 1084 Budapest, Német utca 17-19.
📧 Email: varosuzemeltetes@jgk.hu
📞 Phone: +36-1-782-3537

Thank you for your understanding and patience!

Oszd meg