Parking Lot Striping is Scheduled to begin in Józsefváros

The application of road markings across the district is the implementation of the Participatory Budgeting winning idea of 2025.

Between 4 May and 30 June 2026, a total of 1,241 parking spaces will be marked throughout the district. The works will be carried out in a phased manner across multiple locations from early May until the end of June.

Schedule

Tömő utca

  • 4 May – between Szigony utca and Balassa utca (odd-numbered side)
  • 5 May – between Szigony utca and Balassa utca (even-numbered side)
  • 6 May – between Balassa utca and Füvészkert utca (odd-numbered side)
  • 7 May – between Balassa utca and Füvészkert utca (even-numbered side)

Práter utca

  • 11 May – between Szigony utca and Molnár Ferenc tér (even-numbered side)
  • 12 May – between Szigony utca and Molnár Ferenc tér (odd-numbered side)
  • 13 May – between Molnár Ferenc tér and Füvészkert utca (even-numbered side)
  • 14 May – between Molnár Ferenc tér and Füvészkert utca (odd-numbered side)
  • 18 May – between Füvészkert utca and Illés utca (even-numbered side)
  • 19 May – between Füvészkert utca and Illés utca (odd-numbered side)
  • 20 May – Práter utca 58, large parking area between the high-rise buildings
  • 25 May – Práter utca 60, large parking area between the high-rise buildings

Losonci tér

  • 26 May – Losonci tér 6–7, large parking area (high-rise building side)
  • 27 May – Losonci tér 6–7, large parking area (school side)

Additional locations

  • 1 June – Brunszvik Júlia tér
  • 2 June – unnamed street between Leonardo da Vinci utca and Nagy Templom utca
  • 3 June – Szigony utca 43
  • 4 June – Teleki László tér 15–25 (Phase I)
  • 8 June – Teleki László tér 15–25 (Phase II)
  • 9 June – Berzsenyi utca (even-numbered side)
  • 10 June – Berzsenyi utca (odd-numbered side)
  • 11 June – Kenyérmező utca (even-numbered side)
  • 12 June – Kenyérmező utca (odd-numbered side)
  • 15 June – Bezerédj utca (even-numbered side, between Kiss József utca and II. János Pál pápa tér)
  • 16 June – Bauer Sándor utca (even-numbered side)
  • 22 June – Baross utca 111
  • 23 June – Baross utca 119
  • 24 June – Gaál Mózes utca (in front of the church)
  • 29 June – Bláthy Ottó utca (between Elnök utca and Reguly Antal utca)
  • 30 June – Bláthy Ottó utca (between Reguly Antal utca and Vajda Péter utca)

Temporary parking restrictions will be in effect in the affected areas during the one-day marking works.

Motorists are kindly requested to observe the temporary signage and facilitate the works by keeping the designated areas clear.

We appreciate your understanding and patience.