Some of the works may involve temporary restrictions on pedestrian and vehicle traffic, as well as on parking.
From mid-October to early November 2026, phased renovation works, pavement repairs and structural interventions will be carried out at several locations in Józsefváros to improve the safety of both pedestrians and motorists.
The works are scheduled to take place at the following locations and times:
19-22 October
- Dugonics utca 5. – Repair of damaged sidewalk pavement.
19-30 October
- Tolnai Lajos utca 1-3. – Sidewalk level correction.
- Bérkocsis utca 24. – Raising the driveway entrance to sidewalk level.
26-30 October
- Puskin utca 20. – Restoration of a sunken section of roadway in the parking lane.
26 October – 6 November
- Puskin utca 11-13. – Repair of damaged sidewalk pavement.
- Dobozi utca 17. – Investigation and removal of a 3 m³ void beneath the sidewalk adjacent to the building.
2-6 November
- Nagy Templom utca 6. – Repair of damaged sidewalk pavement.
- Nagy Templom utca 14-16. – Replacement of paving stones around the streetlight pole.
Planned date: First week of November
- Alföldi utca 20. – Repair of the damaged and sunken section of sidewalk next to the Hungarian State Treasury garage exit.
Some of the works may involve temporary restrictions affecting pedestrian and vehicular traffic.
Residents and road users are kindly requested to exercise extra caution during the above periods and to follow all temporary traffic signs and on-site instructions.