In addition to the road section, the sidewalk on the odd-numbered side of the street will also be renovated.
Roadwork will begin on Lovassy László utca at 8:00 AM on September 21, 2026. The goal of the project is to improve the quality of the road network and enhance traffic safety.
Planned completion of the works: October 16, 2026. During this period, a full road closure will be in effect on Lovassy László utca, and traffic changes should be expected on Tavaszmező utca. Access to underground garages on Lovassy László utca will remain guaranteed before 8:00 AM and after 5:00 PM.
During the renovation, the entire wearing course of the roadway will be removed. Because the road sub-base is damaged in several places, structural repairs will be carried out in those sections before applying new pavement layers across the entire road surface.
The works involve laying a binding course approximately 5–8 cm thick, topped with a 3–5 cm wearing course of AC 11 asphalt. To ensure a high-quality, durable surface, the base will be properly prepared before asphalt laying, and each laid layer will be thoroughly compacted.
Following the milling phase, storm drains, utility shut-off valves, and manhole covers will be adjusted to grade level to ensure proper stormwater drainage once the new pavement is complete.
As part of the project, road markings will also be repainted.
In addition to drivers, pedestrians should pay attention to changes, as renovation work will take place on the sidewalk along the odd-numbered side of the street.
We ask residents and commuters for their patience and understanding while the works are underway.