Sidewalk reconstruction works at Teleki László tér

Sidewalk reconstruction works will commence at Teleki László tér, on the section between Dobozi utca and Karácsony Sándor utca, following the completion of public lighting development works.

The construction will take place between June 29 and July 24, 2026, in two phases, as detailed below:

Phase 1:
June 29 – July 9, 2026
Sidewalk reconstruction on the even-numbered side of Teleki Square, between Dobozi Street and Lujza Street.

Phase 2:
July 13 – July 24, 2026
Sidewalk reconstruction on the even-numbered side of Teleki Square, between Lujza Street and Karácsony Sándor Street.

During the works, temporary restrictions can be expected in the affected areas. It is anticipated that 1–2 parking spaces will need to be temporarily closed for the duration of the construction.

We kindly ask residents and road users for their patience and cooperation during the renovation period. The aim of the works is to make the public space safer and more comfortable.